Build the schedule from your rates.
Estimate foundation, racking and module workdays, crew-days, weather allowance and calendar duration from user-supplied quantities and production rates.
Project inputs
Defaults are examples, not recommendations. Replace them with traceable project assumptions.
Screening result
Updated from the inputs at left.
Preliminary decision support only. Confirm inputs, governing standards and final conclusions with the responsible qualified professional before design, procurement or construction.
Method and assumptions
Each phase duration is quantity divided by crews and the entered per-crew daily rate. Sequential duration adds the three phases; the overlap scenario uses the longest phase. Weather allowance applies to production duration before inspection days.
- Crew-days preserve the labour demand before calendar compression.
- Calendar weeks use the entered working week.
- Compare sequential and overlapping cases deliberately.